| Drag and drop remarks | 
Drag and drop is an important feature in Agenda At Once that we paid certain amount of attention to. In this chapter, we will explain how it works.
To-do
| Target | How can be recognized? | What happens? | 
| To-do | ||
| Another to-do task | Another task's description is marked as selected | Task becomes a subtask of second task | 
| At empty (white) area of the to-do list | No secondary task is selected and no blue line | Task is moved to the root level | 
| Between two to-do tasks (on the same level) * | Blue line between tasks | Task is moved between two tasks | 
| Between two to-do tasks (on the different level) * | Blue line between tasks, but note small arrows at line ends | Arrow orientation UP: task is moved after first task (on the same level as first task) 
 Arrow orientation DOWN: task is moved before second task (on the same level as second task) | 
| Schedule | 
 | |
| Date number in monthly calendar | Calendar date is changed and planner refreshed | Task is scheduled to the day that mouse points to | 
| Graphical planner | / | Task is scheduled to the exact time (or day in case target is weekly or monthly planner) | 
* Indicated targets are possible only if Manual sorting is on
Scheduling explanation
When to do task is scheduled, this is what happens:
| • | Copy of to-do task is made and placed into the schedule at specific date and time (working time if not specified otherwise) | 
| • | Duration of second task is same as duration of original task | 
| • | Both tasks become linked to each other | 
| • | Number of linked tasks and scheduled duration are updated in the to-do list | 
| • | In case of scheduling several tasks at same time, they appear one after another | 
Schedule
| Target | How can be recognized? | What happens? | ||||||||
| Planner bounds (without Ctrl key) | Four-arrow mouse pointer | Moving task around (changing time and/or date if multiple days are visible) | ||||||||
| After pressing Ctrl key | Pointer changes to an arrow with rectangle that represents a paper | Task is "unglued" from the planner, and now it's possible to drop it outside (see below) | ||||||||
| Anywhere on the schedule pane | / | Depending on drop target, task is moved to a specific day and time 
 Basically same as moving to-do task to schedule (see above) | ||||||||
| To-do list | / | If task is linked to to-do task 
 
 
 If task is NOT linked to to-do task 
 
 | 
We would like to emphasize different behavior when it comes to moving task from to-do to schedule and vice versa. This could seem illogical at first sight, so allow us to explain the meaning.
To-do task moved to schedule: "I want to focus on this task at a specified time". Both, to-do and scheduled tasks exists now (i.e. task is copied).
Scheduled task moved to to-do list: "I will not focus on this task at this time, and I don't know when I will focus to this task yet" or "I want to postpone this task". Scheduled task is removed, to-do task is created if it doesn't exists (i.e. task is moved).
See also